OverviewThe 2nd and 3rd phase of the C-Power project are the industrial phases following the 1st phase considered as a pilot phase. Phase 2 and 3 consist of 48 6M Repower turbines (24 in each concession sub-area), the installation of the Offshore Transformer Station (OTS) and the installation of the 2nd 150 kV export cable. The wind turbines are built on jacket foundations and are connected together and to the OTS by 33 kV cables.
Construction was started on November 25th, 2010 and is still ongoing (further details of the construction are available in the section Effective Works). Supply and works executionThe turbines were provided by Repower who is responsible for the supply, Operation and Maintenance of the wind turbines during the first 10 years of exploitation (including a possible extension for 10 additional years). |