 |
|
| |
|
| |
EXECUTION PHASE I
WEEK 16
| 1. OCS HVM: |
Preparation workyard Onshore
Construction Site "Halve Maan" |
| 2. HDD: |
Horizontal Directional Drilling for the landfall
of the 150kV seacable |
| 3. GBF: |
Gravity Base Foundation |
| 4. CON: |
Cables Onshore |
| 5. COF: |
Cables Ofshore |
| 6. MAC: |
Marine Activities |
1.
OCS HVM
|
Works
on the new quay wall complete |
 |
2.
HDD
|
|
3. GBF
|
|
Installation of auxillaries
D1 |
 |
Selfpropelled
hydraulic platformtrailers for transport on land of the GBF |
 |
|
 |
Painting of the splash zone
D2 |
Preparation of the painting
works D3 |
Construction of the upper platform D4 |
Cylindrical
part fourth phase D5 |
Construction of the upper
platform D6 |
The
transformer for phase 1 arrives in Slijkens |
 |
Site
installation started for the construction of the landfall cofferdam |
 |
| Construction
of multi purpose pontoon Thornton 1 |
 |
Preparation
of the shear leg crane Rambiz and the lifting frame for the GBF |
 |
Rambiz tug and anchorhandling
vessel |
 |
Preparation
of the gravel bed for the GBF
|
|
| |
Scheldedijk 30 - Haven 1025 - 2070 Zwijndrecht, Belgium - Tel. + 32-3-250 55 51 - Fax + 32-3-250 55 52 - E-mail: c-power@c-power.be |