GENERAL INFORMATION
| wind turbines |
Phase I: 6*5MW - Phase II: 24*5,25MW -
PhaseIII: 24*6MW |
| total capacity |
300
MW |
| water depth |
12
to 27,5 m |
| distance to the coast |
27
to 30 km |
| start construction |
May
2007 |
| start
production |
start 2009 |
| Annual generation |
1000
GWh
= Enough energy for the annual consumption of 600.000 inhabitants |
| Avoided CO2 emission |
450,000 tonnes/year (compared with the environmentally most friendly gas power stations) |
=
the annual CO2 absorption of a forested area of 87,668 ha
= a strip of forest 15km wide along the entire Belgian coastline
= 4 x the area of public forest within the Flemish Region |
| =
1/3rd of the Belgian renewable energy target by 2010 |
| |
 |
|
| |
Scheldedijk 30 - Haven 1025 - 2070 Zwijndrecht, Belgium - Tel. + 32-3-250 55 51 - Fax + 32-3-250 55 52 - E-mail: c-power@c-power.be |