GENERAL PLANNING

2007 - 2009
phase I
Demonstration phase: construction of 6 turbines, 1st wind measuring mast and the 1st electricity cable: 150 kV (40 km)
2009 - 2010
phase I
Monitoring phase
2010 - 2012
phase II
construction of 24 turbines and the offshore transformer station

2012 - 2013
phase III

construction of 24 turbines, 2nd wind measuring mast, 2nd electricity cable: 150 kV (40 km)